Hands On Children’s Museum

Project Highlights

  • Warm water loop from waste water plant heated by a waste heat methane boiler
  • State of the air Energy Management System (EMS)
  • 40% energy use reduction over ASHRAE baseline

Project Cost:

Through the value engineering / redesign process Sunset Air saved the owners $100,000 while providing a system that meets the owner’s needs, and increased the LEED rating from a goal of Silver to a LEED Gold rating in this extremely efficient building

LEED 2014 GOLD

Project Type

Private Public Partnership Design/Build & LEED Gold

Roles

LEED Management, value engineering services that reduced the project cost by over $100,000, design build services for HVAC, water source heat pumps using warm water loop heated by waste heat (methane boilers) from a nearby waste water treatment plant, energy management system (EMS). On Going Service and Maintenance

Facility Description

60,000 square foot interactive educational facility for Children’s Museum