Centennial Elementary

Project Highlights

  • 100% mechanical HVAC demolition
  • Complete change of fuel type to natural gas
  • Interior mechanical mezzanines constructed
  • State of the air Energy Management System (EMS)
  • 90 day start to completion during summer months

Project Cost

$1,300,000

Roles

LEED Management, design build services for HVAC, outdoor geothermal loop, energy management system (EMS), photovoltaics, and plumbing design.

Facility Description

Three story 25,310 square-foot educational facility for the College of Engineering.

Project Highlights

  • Geothermal HP system
  • 90+ % Effective Air to Air heat recovery system.
  • State of the air Energy Management System (EMS)
  • Photovoltaic array producing 20KWH Annually
  • 73% energy use reduction over ASHRAE baseline